Baseline and forecast hours

How planned hours (baseline) and forecast hours are set, how each one changes, and which figures in Consult use them.

Every resource on a project carries two sets of weekly hours: planned hours (baseline) and forecast hours. They look alike on the schedule, but Consult uses them for different jobs, so keeping each one in its role is what makes the project figures meaningful. See hour types for how they relate to actual and billed hours.

The difference between the two

The two hour types answer different questions:

Hour typeQuestion it answersHow it behaves
Planned hours (Baseline)What was agreed?Fixed when the project is sold, and only changed on purpose.
Forecast hoursWhat is expected from here?Updated throughout the project as the work and the people change.

The baseline is typically aligned to the purchase order. It is the yardstick that progress, overruns, and revenue are measured against, so it should stay still while the work moves around it.

The forecast is the live plan. It drives capacity, resource approvals, and the expected revenue for the weeks ahead, so it should always reflect the latest view of the project.

How the baseline is set

A project has only forecast hours until it is sold. Planning before the sale, including pipeline and proposal work, is done entirely in forecast hours.

When a project is moved to Sold, Consult copies each resource’s forecast hours into their planned hours (baseline), week by week. Archived resources are left out of the copy. From that moment, the two sets of hours start out identical and then go their separate ways as the forecast is updated.

Moving a project on to In Progress or Completed does not touch the baseline.

Warning: The baseline is captured every time a project is moved to Sold, not only the first time. If a project is moved back to an earlier status and then to Sold again, the baseline is replaced with the forecast at that moment, and any edits made to the baseline in the meantime are lost.

A resource added to the project after it was sold has no baseline hours. The schedule shows “To plan: No baseline hours” for that resource until baseline hours are entered for them.

How the baseline changes

After the sale, the baseline only changes when someone deliberately edits it. This is intended for a change to the agreement itself, such as a variation order or a revised purchase order.

To edit the baseline on the project schedule:

  1. Click Actions > Edit Planned Hours (Baseline).
  2. Enter the planned hours (baseline) in the weekly cells.
  3. Click Save, then confirm the change.

The baseline can also be set by a schedule import that includes a Planned (Baseline) row.

Changing the project’s start or end date rebuilds the schedule around the new period. Weeks that fall outside the new period are removed, together with their baseline and forecast hours.

The following never change the baseline:

  • Editing forecast hours on the schedule.
  • Automatic rollover of unworked hours.
  • Align Forecast to Actuals.
  • Employees capturing time on their timesheets.

How the forecast changes

The forecast is expected to move throughout the project. It changes when:

  • A project manager edits the weekly hours on the schedule, which is the default editing mode.
  • A resource manager adjusts the hours while reviewing a resource request.
  • Automatic rollover moves a resource’s unworked hours into their upcoming weeks.
  • Align Forecast to Actuals overwrites the forecast of every past week with the hours actually worked.
  • A schedule import includes a Planned (Forecast) row.

Where the baseline is used

Project schedule

The project schedule shows the baseline alongside the forecast:

  • Baseline: The resource’s planned hours (baseline) and their value, shown when Planned Hours (Baseline) is ticked under Show.
  • To plan: The baseline hours less the actual hours worked, which is the part of the agreed hours not yet used.

See allocate hours on the project schedule for how to read To plan.

Project overview

The financials on the project overview use the baseline in the following places:

  • Purchase Order Value: The planned hours (baseline) multiplied by the rates.
  • Invoiced Value card: The percentage underneath is the invoiced value as a share of the baseline value.

Project insights

The Project Insights page measures progress against the baseline:

  • Burn Rate: The actual hours divided by the baseline hours up to today.
  • Burn Rate (Cost): The baseline value up to today divided by the actual cost.
  • Projected Revenue Loss: The estimate at completion less the purchase order value, where the purchase order value is the baseline value.
  • Estimate to Completion (ETC) and Estimate at Completion (EAC): These are calculated from the forecast, but are only shown once there are baseline hours up to today.
  • Charts: The planned (baseline) line on the cash flow and S-curve charts.

Deliverables

The deliverables table shows Total Baseline Hours for each deliverable. The column is not shown on WBS with Resource Scheduling projects.

Invoices

The invoice page uses the baseline in the following places:

  • Show Planned Hours (Baseline): Adds the baseline hours and value to each week, resource, and deliverable, marked PB.
  • Fill Hours: The Planned (baseline) option fills the invoice hours from the baseline.

Company dashboard

The Company dashboard uses the baseline in the following places:

  • Baseline: The original planned billable value for the selected month.
  • Work at Risk: The overrun list shows projects whose actual value has gone above their baseline value, and by how much.

Exports

The baseline is included in the following exports:

  • The schedule export, when Include Planned Hours (Baseline) is ticked.
  • The resource allocations export, as planned baseline hours to date.
  • The Cash Flow Report, opened from an invoice.

Where the forecast is used

The forecast is used wherever Consult needs the current expectation rather than the agreement:

  • Capacity: The available hours on the schedule, and the red highlight when a resource is over capacity, are calculated from forecast hours across all projects.
  • Resource requests: Adding forecast hours in a current or future week is what raises an allocation request for the resource manager.
  • Utilisation: Forecast utilisation for future days and months is based on forecast hours.
  • Hour management: A resource can be locked once their actual hours reach their forecast hours on the project.
  • Notifications: The daily alert when a resource reaches their forecast hours.
  • Forecast Value on the project overview, shown once the project is sold.
  • Compliance to Plan on the project overview: The actual hours divided by the forecast hours.
  • Estimate at Completion (EAC) on the project insights page: The actual cost plus the forecast cost of the weeks still to come.
  • Forecast Revenue and Revenue Leakage on the Company dashboard.
  • Fill Hours on the invoice page, using the Forecast option.
  • The progress bar on the timesheet, which compares the hours captured with the forecast hours to date and in total.

See metric calculations for the formulas behind the project figures.

Keep each hour type in its role

Because so much depends on each hour type, swapping them, for example keeping the agreed plan in the forecast and the latest plan in the baseline, gives misleading results throughout Consult:

  • Capacity and resource requests are worked out from the agreed plan instead of the latest plan, so resources look free or overbooked when they are not.
  • Automatic rollover and Align Forecast to Actuals rewrite the forecast, so they would overwrite the agreed plan.
  • Moving the project to Sold again would replace the latest plan with the agreed plan.
  • The purchase order value, burn rate, overrun list, and other baseline figures measure against a plan that keeps moving, so they no longer show how the project is tracking against what was agreed.

To keep the figures reliable:

  1. Before the sale, build the agreed plan in forecast hours.
  2. Move the project to Sold to capture that plan as the baseline.
  3. During the project, keep the forecast up to date as things change.
  4. Edit the baseline only when the agreement itself changes, such as a new or revised purchase order.