Permissions required

Only users that have Set Admin Settings as part of their role can access the data exporter tool.

Note: If you can access Tools > Data Exporter in the top navigation, you have sufficient permissions.

Use the data exporter

To export data:

  1. From the navbar, go to Tools > Data Exporter.
  2. Choose an export from Select Query. A short description of the chosen export is shown beneath the field, and a sample of the output where one is available.
  3. Complete the inputs the chosen export asks for. Only the fields that export needs are shown, and a field marked with * cannot be left blank.
  4. Click Export.

This downloads an Excel file with the requested data.

Note: The list of exports can differ between Consult clients, since an export can be limited to specific ones. Only the exports available to your organisation are offered, and an export that is not offered cannot be run.

User timesheets export

This option exports the weekly timesheet statuses of all users for the current month.

This export applies to the current month, so no date input is required. The exported file is named in the format User-timesheets-overview-{YYYY-MM-DD HH_MM_SS}.xlsx.

The export is generated from the following:

  • Time scope: The current month and year at the time of export.
  • Users: All users with an active account.
  • Status: For each week, the submission for each user, using its status if present.

Data in the spreadsheet

Headings are generated from the past four weeks, including the current week.

The columns in the spreadsheet:

Column headings in the timesheet export spreadsheet

The row data in the spreadsheet:

Row data in the timesheet export spreadsheet

Project timesheet hours export

This option exports every timesheet line captured against the projects you choose, priced at the rate each week was booked at. It is the export to use to verify what a project cost, or to reconcile captured hours against what was billed.

Complete the inputs as follows:

  • Projects: Required. Choose one or more projects to report on.
  • From Date and To Date: Optional. Leave both blank to export every line ever captured against the chosen projects.

The exported file is named in the format ProjectTimesheetHours-{from}-to-{to}.xlsx when both dates are given, and ProjectTimesheetHours-{YYYY-MM-DD}.xlsx, using the date of the export, when they are not.

Columns in the spreadsheet

One row is written per captured timesheet line, with the following columns:

ColumnContents
Project CodeThe code of the project the line was captured against.
Project NameThe name of that project.
Resource NameThe user who captured the hours.
DeliverableThe deliverable the time went to, for WBS projects. Blank for others.
Timesheet CommentThe comment the user captured on the line.
DateThe date the hours were worked, as YYYY/MM/DD.
Project RateThe rate that applied in that week, not the resource’s current rate.
Hours CapturedThe hours on the line.

Rows are sorted by project code, then resource, then deliverable, then date. Two footer rows close the file: Total Hours and Total Cost, the latter being every line’s hours multiplied by its own week’s rate.

Only lines that carry hours are exported. A day the user left blank or captured as 0 still has a timesheet row behind the scenes, but it is a placeholder rather than captured time, so it is left out.

Note: A resource whose rate changed partway through a project bills each week at the rate that week was booked at. The export reflects that, so the total cost of a project can differ from the same hours priced at the resource’s current rate. See understanding rate changes.

User expense items export

This option exports all expense claims submitted in Consult for a given period. The export contains multiple sections, rendered as separate tables in a single spreadsheet. The exported file is named in the format AllUsers-ExpenseReports-<dateRange>.xlsx.

Sections in the spreadsheet

The export organises data into sections, each with its own set of columns:

  • Disbursements: Expenses where the Type is Meals or Toll Fees.
  • Travel: Mileage claims.
  • Accommodation: Expenses where the Type is Accommodation.
  • Other: All other expenses.
  • Totals: Subtotals by category and a grand total.

Expense reports export

This option exports all approved expense reports submitted through Consult for a selected date range. It provides a bulk overview of approved expense reports, including the people involved in approval and payment.

Set the period to export in From Date and To Date. Both are required. The exported file is named in the format ExpenseReports-{from}-to-{to}.xlsx.

Data in the exported spreadsheet

The columns in the spreadsheet:

Column headings in the expense report export spreadsheet

The row data in the spreadsheet:

Row data in the expense report export spreadsheet

Project resource allocations export

This option exports every resource on your projects, with its rate and its baseline, forecast, actual, and invoiced hours up to a chosen date. It is the export to use to compare what each resource was planned, forecast, worked, and billed across all projects at once.

Complete the inputs as follows:

The Data Exporter with Project Resource Allocations selected, and its As At Date and checkboxes highlighted

  • As At Date: Required, and set to today by default. The hours are counted up to and including the week of this date, and the rate is the one booked for the latest week up to it.
  • Include Projects Not In Progress: Unticked by default, so only projects that are in progress are exported. Tick it to include projects at any other stage.
  • Exclude Open Slots: Unticked by default. Tick it to leave out resources that have no user assigned.

The exported file is named in the format ProjectResourceAllocations-as-at-{YYYY-MM-DD}.xlsx.

Project resource allocations columns

One row is written per project resource, sorted by project name and then employee name:

A sample of the project resource allocations export spreadsheet

ColumnContents
Project NameThe name of the project.
Project StageThe project’s status, for example In Progress.
Employee NameThe user assigned to the resource. Blank for an open slot.
Employee StatusActive or Deactivated. Blank for an open slot.
DesignationThe resource’s designation.
Project Start DateThe project’s start date.
Project End DateThe project’s end date.
Export DateThe As At Date the export was run for.
RateThe rate booked for the resource’s latest week up to the as at date.
Planned Baseline HoursThe resource’s baseline hours up to the as at date.
Forecasted HoursThe resource’s forecast hours up to the as at date.
Actual HoursThe hours captured on timesheets up to the as at date.
Invoiced HoursThe hours on invoices that have been marked as sent, up to the as at date.

A resource that has been removed from a project is still exported while it has actual or invoiced hours, so its history is not lost. See hour types for the difference between baseline, forecast, actual, and invoiced hours.

Expense and mileage entries export

This option exports every expense item and mileage claim dated in a period, one row each, with the details of the expense report it was claimed on.

Complete the inputs as follows:

The Data Exporter with Expense and Mileage Entries selected, and its dates and checkbox highlighted

  • From Date and To Date: Required. Items and claims are included by their own date, not the date of the report.
  • Include Rejected Expense Reports: Unticked by default, so items on rejected reports are left out. Items on draft reports are never exported.

The exported file is named in the format ExpenseAndMileageEntries-{from}-to-{to}.xlsx.

Expense and mileage entries columns

Rows are sorted by employee, then expense report, then date:

A sample of the expense and mileage entries export spreadsheet, showing mileage claims

ColumnContents
Employee NameThe user who submitted the expense report.
Start DateThe From Date the export was run for.
End DateThe To Date the export was run for.
Project NameThe project the expense report was submitted against.
Project CodeThe code of that project.
Expense ReportThe name of the expense report.
Expense Report StageThe report’s status, for example Paid.
CurrencyThe currency of the expense report.
CategoryExpense or Mileage Claim.
SupplierThe supplier of an expense.
Expense TypeThe type of an expense, for example Accommodation, or Mileage for a claim.
Registration #The vehicle registration number of a mileage claim.
From and ToThe start and end locations of a mileage claim.
DistanceThe distance of a mileage claim.
Odometer Start and Odometer EndThe odometer readings of a mileage claim.
RateThe rate per kilometre of a mileage claim.
DescriptionThe description of the item.
DateThe date of the item or claim.
AmountThe amount of the item or claim.
ReimburseableTRUE when the item is to be refunded to the employee.
Bill expenses to clientTRUE when the expense report is billed to the client.

The mileage columns are blank on expense rows, and the expense columns are blank on mileage rows.

Employee hours and expenses summary export

This option exports one row per employee for a period, with their days worked, their hours split into normal, overtime, and billable, and their expense and mileage claims.

Complete the inputs as follows:

The Data Exporter with Employee Hours and Expenses Summary selected, and its dates and checkboxes highlighted

  • From Date and To Date: Required.
  • Include Deactivated Users: Ticked by default. Untick it to leave out users who were deactivated before the From Date.
  • Include Users with 0 Actual Hours: Ticked by default. Untick it to leave out users who captured no hours in the period.

The exported file is named in the format EmployeeSummary-{from}-to-{to}.xlsx.

Employee summary columns

Rows are sorted by employee name, and a deactivated user’s name ends in [Deactivated]:

A sample of the employee hours and expenses summary export spreadsheet

ColumnContents
EmployeeThe user’s name.
Start DateThe From Date the export was run for.
End DateThe To Date the export was run for.
Days WorkedThe number of days in the period with hours captured.
Total HrsAll hours captured in the period, on projects and tasks.
NormalThe total hours less the overtime.
OvertimeThe hours captured above the user’s expected hours, as explained below.
BillableThe hours captured on billable projects.
Expenses TotalThe total of the user’s expense items dated in the period.
Mileage (km)The total distance of the user’s mileage claims dated in the period.
Mileage TotalThe total amount of those mileage claims.
CurrencyThe currency of the expense and mileage totals. Blank when the user claimed nothing.

Overtime is worked out per week, from Monday to Sunday. Any hours captured in a week above the user’s expected hours for that week count as overtime, where the expected hours are the user’s daily hours for each working day, less public holidays and approved leave. A user with no daily hours set has no overtime. When the period starts or ends partway through a week, the whole week is still judged, and only the overtime that falls on days inside the period is counted.

Expense and mileage totals include claims on every report that is past draft and not rejected. A user who claimed in more than one currency has a row for each currency, with their hours on the first row only, so a column total still counts their hours once.

All timesheet entries export

This option exports every timesheet line captured across all projects in a period, priced at the rate each week was booked at. Unlike the project timesheet hours export, it covers every project, and the time captured on tasks, without having to choose them.

Complete the inputs as follows:

The Data Exporter with All Timesheet Entries selected, and its dates and checkbox highlighted

  • From Date and To Date: Required.
  • Exclude Task Timesheets: Unticked by default. Tick it to leave out time captured on tasks, such as non-billable tasks, and keep only project time.

The exported file is named in the format AllTimesheetEntries-{from}-to-{to}.xlsx.

All timesheet entries columns

One row is written per captured timesheet line, sorted by date, then employee, then project code:

A sample of the all timesheet entries export spreadsheet

ColumnContents
Employee NameThe user who captured the hours.
DesignationThe user’s designation on the project. Blank for task time.
Start DateThe From Date the export was run for.
End DateThe To Date the export was run for.
Project NameThe project the line was captured against. Blank for task time.
Project #The code of that project.
DeliverableThe deliverable the time went to, or - on a project line without one.
CommentThe comment the user captured on the line.
DateThe date the hours were worked.
Project RateThe rate that applied in that week, converted to your base currency. Blank for task time.
Time SpentThe hours on the line.
Total Cost (base currency)The hours multiplied by the rate, in your base currency, for example Total Cost (ZAR).

As with the project timesheet hours export, only lines that carry hours are exported, and a line is priced at the rate its own week was booked at.